The CEBU Link JV consortium, formed by ACCIONA and the Philippine companies First Balfour and D.M. Consunji Inc, were the winners of the international competition for the construction of a connection between the islands of Cebu and Mactan in the Philippines. The end customer is the Cebu Cordova Link Expressway Corporation concessionaire, owned by the Metro Pacific Tollways group.

The project, carried out under the Early Contract Involvement (ECI) modality, has an approximate budget of 400 million USD and aims to alleviate the intense traffic between Córdova – capital of the island of Cebu and the second largest city in the Philippines – and the Mactán where the airport of said city is located. Works began in 2018 and the bridge is expected to be completed in the last quarter of 2021 and full operations are expected in the first quarter of 2022.

To make the connection, the project foresees the execution of a new section of road that for the most part runs on water, for which part is located on embankments and part on various structures. Of these, the main and reference work of the action consists of a unique bridge over the navigation channel of the port of Córdova resolved by means of a cable-stayed solution with a central span of 390 m span.

The engineering of the project has been entrusted to the UTE SENER-CFC, companies that also carried out the studies during the preparation phase of the offer. Within the design team, CFC has been in charge of the study and development of the main bridge.

Bridge Features:

The winning solution, proposed by the CEBU Link JV consortium during the bidding phase that will be developed and built from now on, is based on the reference design developed for Metro Pacific by the Danish engineering company COWI, which established a main span of 390 m span, a solution of central towers with axial bracing of a deck with a box section, a standard geometry for the towers and piers.

During the offer phase, and respecting these conditions, the CFC engineers together with ACCIONA’s technical services developed a solution to optimize the global behavior of the structure and its construction. The selected solution introduced some significant changes in the work:

  • Longitudinal configuration: reduction of the total length of the main bridge by shortening the compensation spans, length of the voussoirs, number of stay cables, introduction of intermediate piers in the retaining span, internal counterweight to the caisson to reduce the vertical prestress of anchorage to the holding piles…
  • Cross-section of the deck: reduction of the depth from 4.00 m to 3.50 m, elimination of the transverse ribs to leave projections with a solid slab, greater inclination of the webs, connection of the braces with the box by means of interior props…
  • Foundations: change of the foundation by means of caissons to drilled piles
  • Solution for anchoring the braces in the tower: by means of metallic boxes not connected to all the walls of the tower with the original design.

The final solution for the main bridge consists of a symmetrical cable-stayed structure 651.50 m long with a span distribution of 5.75-60-65-390-65-60-5.75. The 5.75m spans correspond to extensions from the end piers to accommodate half hinges to support the transition spans between the main bridge and the precast girder girders of the access viaducts.

The deck is configured with a prestressed concrete box section with a constant depth of 3.50 m and 26.90 m wide along most of its length. At one end it progressively widens up to 30.0 m to accommodate some branches of the accesses that connect with the trunk. On the other side it narrows to 22.40 m to connect with the accesses to Mactán.

The stays are produced by means of 17 pairs of stays from the axis of the box to two vertical towers with a total height of 140 m, 91 m above the deck. The section of the tower is octagonal with variable dimensions in both elevations. In the upper part, some metal sheets are added externally with which the geometry of a 40 m cross is drawn on each of the faces of the tower, an ornamental element foreseen in the base solution with which we want to pay tribute to the importance of Cebu as the first place of presence of the Catholic Church in the islands.

The foundations are of the deep type with 2.00 or 2.50 m diameter drilled piles deepened in the substrates present in the area, in which substrata of degraded coral rock and deposits of volcanic origin appear under the recent clayey and sandy deposits.

From the point of view of design, the project is a great challenge because in addition to the strong design constraints -among which the fact that the work is in an area of ​​strong seismicity and typhoons stands out- the construction period is tremendously tight.

Noticias

The Bascule Estacio Bridge as the setting of the new PepsiCo´s Mountain Dew commercial.

Mountain Dew, a soft drink of the PepsiCo Group, has chosen our bascule Estacio Bridge in Murcia as the setting for the shooting of its latest and boldest advert. Mountain Dew is a soft drink produced by the PepsiCo Company. Originally, in 1948, it was only advertised in the USA...
By :
Comments : Off

IABSE Symposium to be held in Madrid from 3 to 5 September

    CFCSL participates at IASBE with the following papers: Spanish Bridges (Sesión Plenaria) Javier Manterola Stayed Viaduct in Bucaramanga, Colombia Leonardo Fernández, Lucía Fernández, Guillermo Ayuso, Antonio Cano, Raúl González, Celso Iglesias Design features of the...
By :
Comments : Off

Completion of the structure of the Engordany Roundabout ring

On May 15 2014 the ring of the structure whose construction is underway on the old Massana-bound road at the exit of Escaldes in Andorra was completed. This project is being carried out in collaboration with our partners from SUPORT Enginyers Consultors. The project is an...
By :
Comments : Off

Bridge over the Nervion and Basarab Bridge: another two papers presented by CFC at IABSE 2014

Fourth installment of the papers presented by CFC at IABSE 2014: Bridge over the Nervion in Bilbao and Basarab Bridge in Romania. BRIDGE OVER THE RIVER NERVIÓN ON THE BILBAO DONOSTIA LINE   Leonardo Fernández Troyano y Lucía Fernández Muñoz PDF presentation   Bridge data...
By :
Comments : Off

CFC invited to the First International Bridges Conference in Chile, 2014

Javier Muñoz-Rojas Fernández, an engineer with CFC, has received an invitation to present the paper “Current Possibilities of Cable-Stayed Bridges: Long Spans, Medium Spans and Special Configurations” at the First International Bridges Conference in Chile.  The paper features an...
By :
Comments : Off

The last stay cable installed on La Novena Viaduct in Bucaramanga, Colombia.

(Photo: Laura Herrera / VANGUARDIA LIBERAL) Reproduced herein is the article published in Vanguardia.com (Galvis Ramírez y Cía. SA.) of Bucaramanga, Colombia, on the CFC project of La Novena Viaduct. “The City Hall has announced the final joining of the two parts of La Novena...
By :
Comments : Off

New photographic report of the Cadiz Bay Bridge

In mid-July, the FC engineers Francisco Javier Manterola, Antonio Martínez Cuitillas, Juan Antonio Navarro, Silvia Fuente, Gonzalo Osborne and Borja Martín visited the site of the Cadiz Bay Bridge to ascertain the state of advancement of the works. The visit concluded with a...
By :
Comments : Off

CFCSL wins the bid for the construction of the new bridge over the River Mamoré in Bolivia.

CFCSL has won the contract for the construction project of the Bridge over the River Mamoré in Bolivia, as the specialist on structures of the consortium formed by the firms Euroestudios‐CPS‐Belmonte. The bridge over the River Mamoré is a promise made years ago by the President...
By :
Comments : Off

CFC continues publishing its papers presented at IABSE 2014

Last week we published the first two papers presented by CFC at IABSE 2014 Madrid. Ver . Today we continue with the publication of the “Accessways to the Western Entrance to the ‘Dos Valiras’ Tunnel in Andorra” and the “High-Speed Railway Bridge over the Tera River in Zamora”....
By :
Comments : Off